P1 PHCC is the central Project Health Control project supporting the development, maintenance, promotion and delivery of the PHC Service through the PHC Consortium. The project provides the strategic and operational foundation for introducing PHC Service to commercial organisations managing major projects, programmes and investment portfolios. It brings together the methods, systems, people, evidence, training, communications and delivery arrangements required to establish PHC as a practical project assurance capability. The primary proposition is the application of PHC Service to major commercial projects. Where a company is not yet ready to adopt PHC directly across its core portfolio, it may first commission a controlled pilot using a selected project from its CSR, ESG, sustainability or social-impact expenditure. This gives the company an opportunity to test the service, assess its value and experience the PHC approach before considering wider adoption. P1 PHCC therefore acts as the central project through which PHC Service is developed, demonstrated, governed and progressively introduced into commercial organisations.
A practical 90-day mobilisation plan to embed portfolio control: prioritisation, capacity-based planning, consistent governance, disciplined RAID/change control, and decision-ready MI. The goal is a single source of truth in the PPM tool and a cadence that improves decision speed and delivery confidence.
Create a single, trusted portfolio operating rhythm:
And disciplined control of risks/issues/changes, with the PPM tool used consistently and producing decision-ready reporting.
Portfolio reporting is consistent and trusted (less noise, more decisions).
The PPM tool is the single source of truth for status, RAID, milestones, dependencies and governance.
A working prioritisation + capacity planning process exists and is used.
A sustainable assurance cadence is embedded (lightweight but firm).
The PPMO team has clear roles, templates, and a repeatable way of working.
Phase 1 is about restoring delivery confidence by getting control of the "now": confirming what's in flight, who owns it, what's at risk, and what decisions are needed. The output is a trusted baseline and a lightweight governance cadence that replaces noise with clear, actionable reporting.
Stop drift, reduce confusion, and establish a minimum viable governance cadence.
Build an evidence-based baseline of the portfolio: what exists, what's real, what's at risk.
Stakeholder onboarding: rapid listening tour (Exec sponsor(s), Transformation/Change leads, Finance, key delivery heads). Capture pain points and "must win" outcomes.
Portfolio inventory + data triage: confirm active initiatives, owners, scope, stage, key milestones, spend/budget status, and dependencies.
Set a simple reporting rhythm: weekly portfolio touchpoint + monthly exec pack cadence.
Define minimum standards: status definitions (RAG rules), mandatory fields, RAID ownership, escalation thresholds, change control triggers.
PPM tool reality check: assess current adoption, data quality, and reporting capability; agree the "non-negotiables" for use.
Minimum Governance Set (lightweight): status template, RAID rules, escalation route, change control handshake.
Tool/Data Quality Rules v1: mandatory fields, ownership, update frequency, and reporting cut-off.
≥90% of active initiatives have a named owner + next milestone + current RAG + RAID owner.
Weekly cadence running; escalations are clear and timely.
PPM tool updated to agreed cut-off with ≥90% compliance on mandatory fields.
Phase 2 turns the baseline into predictable delivery: prioritising demand against capacity, standardising governance and assurance, and producing MI that drives faster, clearer decisions.
Turn "busy change activity" into prioritised, capacity-based delivery.
Standardise governance so reporting becomes comparable and decisions are faster.
Phase 3 converts the PPMO from a dependency into a capability. By embedding the decision cadence, standard controls and a clear playbook, the organisation moves from "PPMO pushing" to "teams pulling"—with trusted reporting, fewer surprises and clearer accountability.
Move from "PPMO pushing" to "organisation pulling": adoption becomes normal. Improve delivery confidence through disciplined control and continuous improvement.