BIQ01 - What is the official project or programme name, who is the sponsoring organisation, and who is the accountable executive contact?
Draft 0.1 position: the project is titled Uganda Medicinal Cannabis Development. The sponsoring organisation and formal project owner are not yet established/TBD. PHC is currently providing project-framing and governance support and should not be presented as the owner of the Ugandan Medicinal Cannabis Consortium or the underlying commercial opportunity. Dr Michelle Nyangereka is the known principal contact for initial development, reflecting her involvement with the Consortium steering committee and White Paper. The accountable executive contact, legal entity details and delegated authority remain to be confirmed.
BIQ02 - What strategic need or business problem is the project intended to address?
The project is intended to determine whether and how Uganda's medicinal cannabis opportunity can be developed as a credible, responsible and investable commercial proposition while retaining meaningful value, capability and participation in Uganda. It addresses the present absence of a sufficiently evidenced business model, governance structure, regulatory pathway, stakeholder mandate, investment case and funding-ready proposal. It also addresses the risk that externally led investment could extract disproportionate value without adequate Ugandan participation or public benefit.
BIQ03 - What are the principal project objectives, and how will success be measured?
The principal objectives are to define the opportunity and intended value chain; establish the relevant Ugandan stakeholders and governance arrangements; test legal, regulatory, ethical, agricultural, healthcare, environmental, market and commercial assumptions; compare ownership, operating and investment models; identify how value can be retained in Uganda; support the White Paper; and develop an evidence-based Business Case, Proposal and Funding Readiness assessment. Success measures are not yet approved/TBD. Draft measures should track evidence maturity, stakeholder validation, resolution of material concerns, clarity of the commercial model, governance readiness and whether a rational investment decision can be made.
BIQ04 - What is included within the approved scope, and what is explicitly excluded?
Draft scope includes governance and project definition; stakeholder and evidence mapping; concern, risk, action and decision control; support for the medicinal cannabis White Paper; examination of the commercial opportunity and value chain; assessment of responsible investment and local value retention; and development of the Business Case, Proposal and Funding Readiness position. Explicitly excluded at this stage are any assumption that cultivation, processing, export, clinical use or investment will proceed; commitment of investor funds; promises of returns, jobs or public benefits; legal or regulatory conclusions without specialist evidence; and operational delivery before formal approval.
BIQ05 - What lifecycle stage is the project currently in, and what are the next formal decision or approval gates?
The project is at an early concept and definition stage, represented by Draft 0.1 foundation documents. The next gates should be: validation of the framing by Dr Michelle Nyangereka and appropriate Ugandan participants; confirmation of the sponsoring entity, accountable roles and decision rights; agreement of scope and evidence requirements; regulatory and commercial feasibility review; approval of an outline Business Case; approval of any investment-facing Proposal; and a Funding Readiness decision. Gate owners, dates and approval criteria are not yet established/TBD.
BIQ06 - What governance structure applies, including boards, delegated authorities, decision rights and escalation routes?
No approved governance structure has yet been evidenced. The relationship between PHC, Dr Michelle Nyangereka, the Ugandan Medicinal Cannabis Consortium, its steering committee, any Ugandan legal entity and prospective investors must be defined. Required controls include a named sponsor and accountable executive, documented steering or board membership, delegated authorities, conflict-of-interest declarations, decision and action records, evidence ownership, financial authority, and escalation routes for regulatory, ethical, commercial and reputational issues. Until agreed, governance remains not yet established/TBD.
BIQ07 - Which legal, regulatory, contractual, safety, security or policy obligations most strongly shape the project?
The project is expected to be strongly shaped by Uganda's applicable laws, regulations and government policy concerning medicinal cannabis, controlled substances, healthcare, agriculture, licensing, investment, companies, land, employment, environmental protection, data protection, taxation, export and trade. Contractual ownership, intellectual property, benefit sharing, anti-bribery, sanctions, security, product quality and claims about medical benefit may also be material. The exact obligations and competent authorities have not yet been verified and require qualified Ugandan legal and regulatory input; none should be inferred from this draft.
BIQ08 - What are the most important assumptions, constraints and external dependencies?
Key assumptions requiring evidence include that a lawful and commercially viable pathway may exist; that credible demand and investment appetite exist; and that a model can retain meaningful value and participation in Uganda. Constraints include limited verified information, an unconfirmed project vehicle and governance structure, potential licensing and policy restrictions, market uncertainty, funding availability and the need for stakeholder legitimacy. External dependencies include Ugandan regulatory decisions, participation by the Consortium and other stakeholders, specialist legal and technical evidence, market access and responsible investors.
BIQ09 - What approved baselines currently exist for scope, schedule, cost, risk and benefits, and when were they last reviewed?
No approved baselines for scope, schedule, cost, risk or benefits have been provided. The current material is Draft 0.1 project framing rather than an authorised baseline. Baselines should be established only after the sponsor, governance, scope, evidence plan and initial feasibility work are confirmed, and should then record approval date, owner, assumptions and review cycle. Current status for each baseline: not yet established/TBD.
BIQ10 - What are the three most important decisions or control improvements required in the next 90 days?
The three most important decisions or control improvements for the next 90 days are: first, confirm the sponsoring entity, accountable leadership, steering arrangements and PHC's mandate; second, approve a bounded definition-stage scope with evidence requirements covering regulation, market, value chain, ownership and Ugandan value retention; third, establish controlled registers for stakeholders, assumptions, concerns, risks, actions, decisions, evidence and deliverables, with clear review and escalation arrangements.
PSQ01 - What delivery model is proposed, and how is the programme divided into workstreams, projects or major packages?
The proposed model is a gated commercial-development and governance programme rather than immediate operational delivery. Draft workstreams are: governance and stakeholder mandate; legal and regulatory pathway; market and commercial feasibility; value-chain and operating-model design; responsible investment and Ugandan value retention; White Paper and evidence development; Business Case and Proposal; and Funding Readiness. The final workstream structure, leaders, dependencies and package boundaries are not yet approved/TBD.
PSQ02 - What are the principal deliverables, and what acceptance criteria will demonstrate that each is complete and fit for purpose?
Draft principal deliverables are a validated Project Definition, stakeholder and governance map, controlled concerns/risks/actions/evidence registers, regulatory and commercial evidence pack, options and operating-model assessment, White Paper contribution, Business Case, Proposal and Funding Readiness assessment. Acceptance should require an identified owner and approver, traceable sources, explicit assumptions and uncertainties, documented stakeholder review, resolution or escalation of material concerns, and version approval. Detailed criteria for each deliverable are not yet established/TBD.
PSQ03 - What are the key milestones, schedule drivers and current critical or near-critical paths?
Milestones should include framing validation, governance confirmation, evidence-plan approval, regulatory pathway review, stakeholder consultation, market and value-chain assessment, options appraisal, outline Business Case, White Paper milestone, Proposal approval and Funding Readiness decision. Likely schedule drivers are access to Ugandan decision-makers and evidence, regulatory clarity, specialist advice and agreement on ownership and investment structure. No approved schedule or critical path currently exists; dates and dependencies are TBD.
PSQ04 - How are risks and opportunities identified, assessed, quantified, owned, treated and escalated?
Risks and opportunities should be entered in a controlled register with source, description, cause, consequence, likelihood, impact, proximity, owner, response and review date. Material items should be quantified where evidence permits, linked to assumptions, costs and decisions, and escalated to the appropriate steering or executive authority. Opportunities should be tested with the same discipline as risks, particularly claims about market demand, employment and local value. Ownership, scoring scales, thresholds and escalation authority are not yet approved/TBD.
PSQ05 - How are scope, design, schedule, cost and organisational changes proposed, assessed, approved and incorporated into the baseline?
Changes should be raised through a documented change request stating the reason, options and effects on scope, schedule, cost, risk, benefits, regulation, stakeholders and evidence. The relevant workstream owner should assess the impact; project governance should approve, reject or defer it within delegated authority; and approved effects should be incorporated into controlled baselines and documents. No formal change-control procedure or authority thresholds have yet been agreed/TBD.
PSQ06 - What assurance reviews, stage gates, peer reviews or independent challenges are required, and who has authority to accept the findings?
Required assurance is likely to include peer review of evidence, qualified Ugandan legal and regulatory review, commercial and financial challenge, technical/agricultural and healthcare input where relevant, stakeholder validation, conflict-of-interest review and independent challenge before investment or funding decisions. Suggested gates are concept validation, feasibility, outline Business Case, final Business Case/Proposal and Funding Readiness. The sponsor or properly constituted board should accept findings; those authorities and reviewers are not yet established/TBD.
PSQ07 - How will quality requirements, verification, validation, inspection, testing and non-conformance be controlled?
Each deliverable should have defined quality requirements, evidence sources, reviewer and approver. Verification should confirm completeness, traceability, calculation accuracy, consistency and compliance; validation should test whether the proposal answers the real Ugandan commercial and stakeholder need. Operational inspection or testing regimes for cultivation, processing or products are outside the current definition-stage scope and remain TBD. Non-conformances should be logged, owned, corrected, rechecked and prevented from being treated as accepted evidence.
PSQ08 - What are the most important technical, organisational and contractual interfaces, and how are they managed?
Key interfaces include PHC and the Ugandan project sponsor; Dr Michelle Nyangereka and the Consortium steering committee; commercial, legal, regulatory, healthcare, agricultural and technical contributors; potential investors and funders; and any communities or public bodies affected by future operations. Contractual interfaces may include ownership of evidence, intellectual property, confidentiality, fees, liability and decision authority. An interface register with named owners and information handoffs should be established; current arrangements are TBD.
PSQ09 - What procurement and supply-chain strategy applies, particularly for specialist, long-lead or safety-significant items?
No operational procurement strategy is yet approved. During definition, specialist advice should be procured against clear scopes, competence, independence, conflicts, confidentiality, deliverables and acceptance criteria. If the project advances, cultivation, processing, laboratory, security, logistics and compliance requirements may include specialist or long-lead items, but these must not be assumed before the operating model and regulatory pathway are established. Supplier due diligence, local participation and whole-life value should form part of the future strategy.
PSQ10 - How will commissioning, handover, operational readiness and benefits realisation be planned and evidenced?
Commissioning and handover are not yet applicable to a defined operating asset. For the present phase, handover means ensuring approved documents, registers, evidence, decisions, contracts and obligations pass to a confirmed Ugandan project owner with named custodians and access. Any future operational-readiness plan should cover licences, organisation, competence, systems, facilities, supply chain, security, quality, finance and emergency arrangements. Benefits should have owners, baselines and evidence measures, particularly for Ugandan participation and retained value; all remain TBD.
PEQ01 - Which systems are the authoritative sources for scope, schedule, cost, risk, actions, changes, documents and evidence?
PHC systems may provide the initial controlled environment for project framing, but no authoritative source arrangement has been formally approved. The project should designate a source of truth for scope, schedule, cost, risks, actions, changes, decisions, documents and evidence, with ownership and access agreed between PHC and the Ugandan sponsor. Existing Consortium and White Paper systems should be identified before migration or duplication. Current authoritative systems are not yet established/TBD.
PEQ02 - How are documents numbered, reviewed, approved, revised, distributed, retained and withdrawn from use?
A document-control convention should assign a unique identifier, title, owner, status, version, review date and approver to each controlled item. Drafts should be distinguished from approved documents; revisions should retain history and approval evidence; distribution should be permission-based; superseded versions should be withdrawn from active use but retained according to an agreed schedule. The applicable naming, approval, retention and disposal rules are not yet established/TBD.
PEQ03 - What evidence is required to substantiate reported progress, completed actions, accepted deliverables and closed risks or concerns?
Reported progress should be supported by dated source evidence, approved meeting or decision records, completed and accepted deliverables, and traceable updates to the relevant register. Action closure should require evidence of the agreed outcome and owner/approver confirmation. Risk or concern closure should show that the cause or exposure has been removed, accepted or transferred by an authorised decision, not merely that discussion occurred. Exact evidence standards remain to be approved/TBD.
PEQ04 - How are configuration, version and baseline changes controlled so that teams know which information is current?
The project should use controlled versions and approved baselines with a clear status such as working draft, reviewed, approved or superseded. Proposed changes should be assessed and authorised before the baseline is updated; affected documents, assumptions, costs, risks and decisions should be cross-referenced; and participants should have access to the current approved version. No formal configuration or baseline-control procedure currently exists/TBD.
PEQ05 - What data-quality rules apply, and who is responsible for checking completeness, consistency, timeliness and accuracy?
Data-quality rules should require source attribution, completeness, consistency, currency, appropriate units and definitions, and separation of verified facts from assumptions, estimates and stakeholder views. Each data set or evidence item should have an owner and reviewer, with material claims independently checked where practical. Particular care is needed for legal status, market size, pricing, yields, medical claims, costs, employment and economic benefit. Responsibilities and checking frequency are not yet established/TBD.
PEQ06 - How are confidentiality, security classification, access permissions and personal or commercially sensitive information managed?
Information should be classified according to sensitivity, with role-based access, secure storage and controlled sharing. Personal data, investor discussions, legal advice, commercially sensitive models, regulatory correspondence, stakeholder contact details and unpublished White Paper material may require restriction. Confidentiality and data-processing terms should be agreed before centralising information. Applicable classifications, permissions, consent arrangements and information owners are not yet established/TBD.
PEQ07 - What reporting cycle is used, which dashboards or reports are produced, and who relies on each output for decisions?
A proportionate reporting cycle should be agreed once governance is confirmed. A draft monthly pack could cover scope and milestone status, decisions required, top risks and opportunities, actions, changes, costs and forecast, evidence maturity, stakeholder engagement and Funding Readiness. Workstream reviews may need a shorter cadence. Each output should identify its audience and decision purpose. No approved reporting cycle, dashboard or recipient list currently exists/TBD.
PEQ08 - How are schedule, cost, risk, actions, changes, decisions and evidence linked so that impacts can be traced across the programme?
Traceability should be maintained through unique identifiers and links between milestones, costs, risks, actions, changes, decisions, assumptions, evidence and deliverables. For example, a regulatory uncertainty should link to its evidence request, specialist action, schedule effect, cost allowance and gate decision. A single controlled register or integrated set of registers should provide this chain. The information model and tooling are not yet established/TBD.
PEQ09 - What backup, disaster-recovery, cyber-resilience and business-continuity arrangements protect project information?
Project information should be held in an approved environment with access control, multifactor authentication where available, routine backup, version recovery, malware protection and a tested restoration process. Continuity arrangements should identify essential records, alternate access and responsible contacts if a person, system or location becomes unavailable. Existing PHC, Consortium or sponsor arrangements have not yet been assessed, so backup, recovery and cyber-resilience status is TBD.
PEQ10 - What current information gaps, duplicated systems or manual workarounds create the greatest control risk?
The greatest present control risk is the lack of verified, centrally governed information about project ownership, authority, regulatory status, commercial assumptions, stakeholders and evidence. Existing Consortium and White Paper materials may also sit in separate personal or organisational channels, creating duplication and uncertain version status. The specific systems, spreadsheets, messaging groups and manual workarounds in current use have not yet been inventoried/TBD.
PQ01 - Who holds the principal accountable roles, and what are their responsibilities and delegated authorities?
Known roles are limited. Dr Michelle Nyangereka is the initial contact and is described as involved with the Ugandan Medicinal Cannabis Consortium steering committee and White Paper. PHC currently supports framing and governance documentation. The project sponsor, accountable executive, board or steering chair, commercial lead, finance lead, legal/regulatory lead, technical lead and stakeholder lead are not yet established/TBD. Their responsibilities, delegated limits and accountability must be documented before formal approvals or commitments.
PQ02 - What organisation structure is currently in place, and which key posts are vacant, interim, duplicated or unclear?
No verified organisation chart has been provided. The composition and authority of the Consortium steering committee, relationship to any legal entity, role of PHC and status of contributors all require confirmation. Posts should not be described as vacant or filled until the intended organisation and delivery model are agreed. Current duplicated, interim or unclear roles are therefore not yet established, although accountability between PHC, Michelle, the Consortium and any investors is an immediate clarification need.
PQ03 - What capabilities and experience are essential for the current phase, and where are the most significant gaps?
The current phase needs project governance, commercial strategy, investment and financial modelling, Ugandan legal and regulatory expertise, medicinal cannabis policy, market analysis, agriculture and value-chain design, healthcare/scientific understanding, responsible investment, stakeholder engagement, evidence synthesis and White Paper development. Confirmed capabilities of current participants have not been documented. The most significant gaps are therefore not yet established/TBD, with independent legal/regulatory and commercial evidence likely to be early priorities.
PQ04 - What resource plan exists, including mobilisation dates, demand peaks, scarce skills and reliance on contractors or secondees?
No approved resource plan exists. It should identify named roles, availability, mobilisation dates, decision and evidence deadlines, demand peaks around reviews and funding gates, scarce specialist skills, and any reliance on advisers, contractors or secondees. The plan should distinguish Ugandan leadership and capability from external support and should avoid building a team merely to justify a fee. Headcount, effort, dates and sourcing decisions are not yet established/TBD.
PQ05 - How are contractors, consultants, delivery partners and suppliers selected, instructed, supervised and held accountable?
External parties should be selected through proportionate due diligence covering competence, relevant Ugandan and sector experience, independence, conflicts, legal standing, references, price and ability to transfer value or capability locally. Engagements should use written scopes, outputs, acceptance criteria, confidentiality, intellectual-property terms, reporting, payment milestones and termination rights. A named owner should supervise performance and retain evidence. No approved procurement or contractor-management process currently exists/TBD.
PQ06 - Which organisational interfaces are most vulnerable to gaps, duplication, delay or conflicting authority?
The most vulnerable interfaces are likely to be between PHC and the Ugandan sponsor; the sponsor and Consortium steering committee; governance and prospective investors; commercial ambition and regulatory evidence; White Paper development and investment materials; and external specialist advice and local stakeholder knowledge. These may create gaps, duplication or conflicting authority if roles are not explicit. Actual interface weaknesses have not yet been evidenced and should be mapped with named owners.
PQ07 - What is the formal meeting, review and decision-making rhythm, and how are actions and decisions recorded?
No formal meeting rhythm has been confirmed. A draft model could include regular workstream reviews, a monthly project-control review and steering or board meetings aligned to decision gates, with urgent escalation available between meetings. Agendas should identify decisions required; minutes should record attendance, conflicts, evidence considered, decisions, actions, owners and dates; and registers should be updated promptly. Final cadence, membership and secretariat responsibility are TBD.
PQ08 - What escalation routes and thresholds apply when safety, cost, schedule, quality, commercial or regulatory limits are threatened?
Escalation thresholds should cover actual or threatened legal/regulatory breach, safety or security risk, unauthorised commitments, material cost or schedule variance, quality failure, loss of critical evidence, conflict of interest, misleading public or investor claims and departure from agreed local-value principles. The route should progress from workstream owner to project lead and accountable board/executive, with immediate specialist or authority notification where legally required. Numeric thresholds and named authorities are not yet established/TBD.
PQ09 - What workload, continuity, succession or key-person risks could weaken delivery or assurance?
Potential risks include dependence on Dr Michelle Nyangereka or a small number of contributors, unconfirmed access to specialist Ugandan advice, discontinuity in steering participation, concentration of evidence and relationships in personal channels, and insufficient capacity during White Paper or funding milestones. These are plausible early risks, not confirmed facts. A resource and succession review should identify critical roles, deputies, handover records and realistic availability; current workload and continuity data are TBD.
PQ10 - What behaviours, incentives or cultural factors may discourage challenge, delay escalation or distort reporting?
Possible cultural and incentive risks include enthusiasm for the opportunity suppressing challenge, investor or funding pressure encouraging premature claims, deference to status delaying escalation, unclear ownership obscuring accountability, and financial interests affecting evidence or option appraisal. Equally, fear of controversy could inhibit legitimate exploration. Governance should reward transparent uncertainty, evidence-based challenge, declared conflicts and documented dissent. Actual behaviours and incentives have not yet been assessed/TBD.
FQ01 - What funding sources, approvals and financial commitments currently support the project?
No confirmed funding source, approval or financial commitment has been evidenced. Potential commercial investment, grant or development funding may be considered only after the project vehicle, scope, governance and funding need are clearer. Any PHC contribution, discounted work or offer of humanitarian rates would be a separate pricing decision and should not be represented as project funding or as changing the project's Commercial category. Current commitments are not yet established/TBD.
FQ02 - What is the current estimate or budget, what is its basis, and what level of confidence or maturity does it have?
No approved estimate or budget currently exists. Draft 0.1 does not yet provide enough scope, schedule, resource, procurement, risk or operating-model evidence for a reliable figure. The first estimate should be a bottom-up cost of the agreed definition-stage work, stating rates, effort, expenses, assumptions, exclusions, contingency and confidence range. Later investment and whole-life estimates should be developed only when the commercial model is sufficiently defined. Current maturity: unestablished/TBD.
FQ03 - How are the cost baseline, contingency, management reserve and quantified risk exposure established and controlled?
The cost baseline should be built from approved scope, work breakdown, resource rates, quantities and schedule. Identified risks should be quantified where possible and inform contingency; management reserve should cover defined categories of unknown exposure and remain under higher-level authority. Drawdown and reallocation should require documented approval, and risk exposure should be reviewed alongside forecast cost. No baseline, contingency, reserve methodology or quantified risk model has yet been approved/TBD.
FQ04 - How are actual cost, commitments, accruals, forecast outturn and variance reported and reconciled?
Once expenditure begins, actual invoices and payments, contractual commitments, accruals and forecast remaining cost should be reconciled to the approved cost breakdown and reported at an agreed cycle. Variances should show cause, impact, corrective action and approval status, with changes separated from performance variance. The responsible finance system, reporting period, currency treatment and variance thresholds are not yet established/TBD because no spending history or approved budget has been provided.
FQ05 - Which contract and commercial models are proposed, and where do liability, incentive or risk-allocation concerns remain?
Commercial models may include PHC advisory or governance support under a defined professional-services agreement and, later, alternative investment, ownership, operating, partnership or supply arrangements for the Ugandan opportunity. None is yet selected. Material issues include who owns the opportunity and outputs, how Ugandan value is retained, payment and performance incentives, liability for advice or claims, regulatory responsibility, intellectual property, conflicts and risk allocation. PHC may elect to offer humanitarian rates, but that concession should be transparent and should not convert the project from Commercial to Humanitarian.
FQ06 - What major procurement commitments or long-lead decisions must be made before full certainty is available?
No major procurement commitment has yet been identified. Early decisions may be needed for independent Ugandan legal/regulatory advice, commercial feasibility work and stakeholder engagement before every uncertainty can be removed. Any commitment should be staged, capped and linked to decision-useful outputs. Operational long-lead commitments for land, licences, facilities, cultivation, processing, laboratories, security or logistics must wait until the operating model, regulatory pathway and Business Case justify them. Specific dates and values are TBD.
FQ07 - What current or foreseeable changes, claims, disputes or commercial exposures could materially affect the project?
Foreseeable exposures include changes in Ugandan law or policy, disputes about ownership or mandate, confidentiality or intellectual-property claims, conflicts of interest, inaccurate regulatory or medical claims, investor representations, unapproved commitments, exchange-rate and tax exposure, land or community issues, and failure to deliver promised local value. No current claim or dispute has been evidenced. A legal and commercial issues register should be established, with all actual matters recorded and reviewed; current status is TBD.
FQ08 - How are value, affordability, whole-life cost and alternative options challenged before major commitments are approved?
Major commitments should be challenged against strategic fit, lawful feasibility, evidence of demand, affordability, financing capacity, risk-adjusted value, Ugandan value retention and realistic whole-life costs. Options should include doing nothing, further evidence work, phased pilots, alternative ownership/operating models and different funding structures. Independent review and documented assumptions should precede approval. A discounted or humanitarian PHC rate may improve affordability but must not substitute for proving project value or comparing alternatives.
FQ09 - What financial controls, segregation of duties, audit rights and record-keeping requirements apply?
Required controls should include an approved budget and delegated authority matrix, separation of request, approval, payment and reconciliation where proportionate, verified supplier details, contracts and purchase records, conflict declarations, supporting invoices, bank reconciliation, controlled changes and retention of an audit trail. Investors or funders may require inspection and audit rights. The receiving legal entity, banking arrangements, accounting policy, tax treatment and responsible officers are not yet established/TBD.
FQ10 - What affordability, cash-flow or funding thresholds could cause delay, rephasing or loss of project viability?
No affordability, cash-flow or funding thresholds are yet approved. Definition work may be delayed if funding is unavailable for essential Ugandan legal, regulatory, commercial or stakeholder evidence. Later viability will depend on capital requirement, timing, operating cash flow, financing terms, currency exposure and minimum market or regulatory conditions. The Business Case should identify break points and staged funding gates. PHC's willingness to offer humanitarian rates may reduce advisory cost but does not resolve the wider project's funding or viability thresholds.
MQ01 - Who are the principal internal and external stakeholders, and what authority, influence or exposure does each have?
Principal stakeholders are expected to include the Ugandan project sponsor and accountable executive; Dr Michelle Nyangereka; the Ugandan Medicinal Cannabis Consortium steering committee; relevant Ugandan ministries, regulators and local authorities; commercial, agricultural, healthcare, research and technical participants; prospective investors and funders; workers, suppliers and communities affected by future activity; and PHC. Their formal authority, influence, interests and exposure have not yet been mapped or confirmed/TBD.
MQ02 - What are the principal expectations, concerns and potential points of conflict among those stakeholders?
Likely expectations include a credible commercial opportunity, lawful operation, appropriate returns, local employment and capability, meaningful Ugandan ownership or participation, retained value, transparent decisions and responsible public benefit. Potential conflicts may concern ownership, control, distribution of returns, investor protections, regulatory compliance, land or environmental effects, health claims, pace of development and whose evidence is trusted. These are hypotheses for consultation, not established stakeholder positions.
MQ03 - What communication and engagement channels are used, and how is feedback converted into controlled actions or decisions?
Current communication channels have not been confirmed. The project should agree controlled channels for steering decisions, workstream collaboration, document review, stakeholder consultation and external statements. Feedback should be recorded with its source and consent status, assessed for effect on requirements, risks, actions or decisions, assigned to an owner and closed with a documented response. Use of email, meetings, messaging groups, shared drives or public channels remains not yet established/TBD.
MQ04 - How are regulatory, governmental and local-authority relationships coordinated and documented?
Regulatory and governmental engagement should be coordinated through a named authorised lead, supported by a stakeholder and correspondence register. Meetings, advice, applications, commitments and follow-up actions should be documented and linked to the regulatory evidence base. Technical or legal interpretations should be checked by qualified advisers, and public bodies should not receive inconsistent approaches from different participants. Relevant authorities, existing relationships, engagement permissions and lead responsibilities are not yet established/TBD.
MQ05 - What impacts, benefits or burdens may be experienced by communities, workers, customers and the local economy?
Potential benefits may include Ugandan employment, skills, enterprise development, agricultural and technical capability, tax or export value, healthcare or research opportunities, and locally retained commercial value. Potential burdens include land or resource pressure, unequal benefit distribution, insecure work, environmental impact, security requirements, reputational effects, unmet expectations and external extraction of value. None is an established outcome. Distributional impact and affected groups must be evidenced through the Business Case and stakeholder engagement.
MQ06 - What consultation commitments, undertakings or stakeholder promises have been made, and how are they tracked?
No verified consultation commitments, undertakings or stakeholder promises have been provided. Draft discussions, White Paper participation or expressions of interest should not be converted into promises without evidence and authority. The project should establish an undertakings register recording who made each commitment, to whom, when, under what authority, its exact wording, owner, due date and status. Existing commitments and consultation obligations remain not yet established/TBD.
MQ07 - What reputational risks, misinformation or unresolved public concerns could undermine confidence in the project?
Reputational risks include association with a controlled substance; confusion between medicinal and non-medicinal use; claims of illegality, political favour, foreign extraction or unequal benefit; unsupported health, job or investment claims; conflicts of interest; and premature presentation of the Consortium, White Paper or project as formally approved. Misinformation and public concerns have not yet been assessed. Communications should state what is known, provisional and TBD, with authorised responses and evidence links.
MQ08 - What information should be transparent, and what information must remain restricted for legal, commercial, privacy or security reasons?
The project should transparently report its purpose, governance, approved scope, decision process, material evidence, conflicts, funding sources, high-level costs, stakeholder engagement, key risks and progress, subject to lawful restrictions. Personal data, privileged legal advice, security-sensitive information, investor negotiations, proprietary methods, commercially sensitive forecasts and unpublished regulatory material may require restriction. A publication and classification policy, consent basis, redaction rules and approval authority are not yet established/TBD.
MQ09 - How are lessons learned, stakeholder feedback and operating experience captured and incorporated into future decisions?
Lessons, feedback and operating experience should be captured in meeting records, decision logs, review findings, stakeholder-response records and a lessons register. Each lesson should state the source, implication, proposed change, owner and outcome, and should feed into risks, requirements, options, plans and later-stage designs. Gate reviews should confirm that relevant lessons have been addressed. No formal lessons process or existing operating evidence has yet been identified/TBD.
MQ10 - What concise evidence-based update could be issued regularly to demonstrate project health without overstating certainty?
A suitable regular update would state: current lifecycle stage and decision gate; approved progress against milestones; evidence received and significant gaps; top risks, concerns and decisions required; material scope or cost changes; stakeholder engagements completed; and current Business Case, Proposal and Funding Readiness status. It should distinguish verified facts from assumptions, avoid forecasts of benefit or investment success without evidence, and disclose that key governance and commercial details remain TBD where applicable. Publication audience and approval route are not yet agreed.