RRQ_01: Risk descriptions clarity
1 - Unacceptable
1: <80% descriptions clear
2: >80% descriptions clear (minimum pass)
3: >80% descriptions clear (consistent; few ambiguities)
4: Risk descriptions clear without further reference.
Notes
First pass - pre-review.
RRQ_02: Register contains non-risk/common items / uncertainties
Unrated
1: >20% non-risk/common items
2: <20% issues/uncertainties (minimum pass)
3: <20% issues/uncertainties (stable; actively cleaned)
4: No issues/uncertainties in the register.
RRQ_03: Risks assessed for Manageability
Unrated
1: <80% of risks have been assessed for 'Manageability'
2: >80% of risks have been assessed for 'Manageability' (minimum pass)
3: >80% of risks have been assessed for 'Manageability' (consistent; quality checked)
4: All risks are assessed for 'Manageability'
RRQ_04: Risks approved by Sponsor
Unrated
1: <80% of risks in register approved by Sponsor
2: >80% of risks in register approved by Sponsor (minimum pass)
3: >80% of risks in register approved by Sponsor (consistent; approvals current)
4: All risks in register approved by Sponsor
RRQ_05: Register coverage across project aspects
Unrated
1: Covers only 1 aspect of project.
2: Covers most aspects of project (minimum pass)
3: Covers most aspects of project (consistent; no major blind spots)
4: Covers all aspect of project
RRQ_06: Register freshness: updates, new risks, closures
Unrated
1: Risk in register not updated, new risks not identified, old risks not closed > 2 months
2: Risks updated, new risks identified, old risks closed < 3 months (minimum pass)
3: Risks updated, new risks identified, old risks closed < 3 months (consistent; ageing controlled)
4: Risks register evergreen