Project:
461 - HARP Haweswater Aqueduct Resilience Programme
Description:
Unforeseen geology or groundwater conditions undermine design assumptions and productivity for tunnelling and shaft works.
Desired Outcome:
Ground risks are understood early with mitigation and contingency aligned to realistic confidence levels.
What Could Go Wrong:
Late discovery drives redesign, delay, cost escalation, safety exposure, and claims.
Current Situation:
Ground model exists but uncertainty remains until works expose real conditions; interface between investigation and design can drift.
Action Strategy:
Define ground risk owners; ensure investigation findings are integrated into design; maintain a live ground risk log; set clear escalation triggers; link to schedule risk and contingency.
Concern Category:
T1 Project Scope
Location:
UK
Analysis: Not available