project_id: 461 - HARP Haweswater Aqueduct Resilience Programme - Concerns (10)





Concern #463 - Design Maturity Not Reaching Construction-Ready

Project:
461 - HARP Haweswater Aqueduct Resilience Programme

Description:
Design packages fail to reach stable issue-for-construction maturity in time for mobilisation and sequencing.

Desired Outcome:
Design reaches agreed maturity gates with interface definitions locked before mobilisation.

What Could Go Wrong:
Design churn causes rework, procurement delay, site stoppages, and interface conflict.

Current Situation:
Multiple parties contribute to design; interface definitions can remain ambiguous; maturity gates may be weakly enforced.

Action Strategy:
Implement design maturity gates; track "open design decisions"; assign interface map ownership; tie design freeze to mobilisation readiness checks.

Concern Category:
T2 Design / Eng.

Location:
UK