Project:
461 - HARP Haweswater Aqueduct Resilience Programme
Description:
Testing/commissioning sequence, evidence packs, or operational acceptance requirements are not ready near handover.
Desired Outcome:
T&C readiness is planned early with clear evidence requirements and gate criteria.
What Could Go Wrong:
Late rework and delay at the most expensive project stage; acceptance disputes.
Current Situation:
Handover requirements can be treated as "later"; interfaces between construction and operations are complex.
Action Strategy:
Define T&C readiness gates; map evidence requirements; track readiness actions; include in risk cadence well before handover.
Concern Category:
T4 Construction
Location:
UK
Analysis: Not available
| Snapshot History |
|---|
| C471_260201.pdf |